Electric Resoration Progress from Entergy

New Orleans Neighborhood

Electric Restoration Progress

Electric Service Expected Date of Restoration to customers who can safely receive power

Bywater/Marigny

General Street Boundaries:
Esplanade Ave. to Poland Ave. and St. Claude to the Mississippi River

Completed repairs to infrastructure in the area, working to restore individual customers.

Customers who can take power should have power, except for several isolated cases.

Portions of Treme/Bywater/Marigny
 

General Street Boundaries:
N. Claiborne to St. Claude and Esplanade Ave. to Poland Ave.

Currently making repairs to the infrastructure serving the area. Damage assessments substantially complete.

7 days for customers who can take power.

Hollygrove/Broadmoor

General Street Boundaries:
70125 Area

Completed repairs to infrastructure in the area. Customers will need a permit from New Orleans Dept. of Safety and Permits before Entergy can restore power.

Customers who can take power should have power.

Mid City

General Street Boundaries:
Expressway to City Park Avenue and N. Carrollton to N. Claiborne

Crews have repaired the infrastructure and have restored power were possible. Several homes in the area experienced flooding.

Customers who can take power should have power, except for several isolated cases

Esplanade Ridge

General Street Boundaries:
Dumaine to Wisner and Paul Morphy (off N. Broad) to O-Reilly

Crews have repaired the infrastructure and have restored power were possible. 

Customers who can take power should have power, except for several isolated cases

Uptown - Lakeside of St. Charles Ave.

General Street Boundaries:
St. Charles Ave. to Freret and Carrollton to Expressway

Infrastructure repairs to Freret St. Crews are working to repair infrastructure from Freret to S. Claiborne where homes experienced severe flooding - infrastructure repairs may take two weeks in that area. 

Customers who can take power should have power, except for several isolated cases.

Uptown - Riverside of St. Charles Ave.

General Street Boundaries:
St. Charles Ave. to Mississippi River and S. Carrollton to Expressway

Restoring power to customers who can safely receive power.  

Customers who can take power should have power, except for several isolated cases.

Carrollton

General Street Boundaries:
S. Carrollton to Monticello Ave. (parish line) and Leake Ave. to Oak St.

 

Infrastructure repairs were made from Oak Street to Earhart, but customers will need a permit to receive power.

Customers who can take power should have power, except for several isolated cases.

Lakeshore Park -- Lake Terrace/Lake Vista East/Lake Vista West

General Street Boundaries:
Lake to Robert E. Lee; Robert E. Lee to Lake Pontchartrain and Pratt to Leon C. Simon

Completed repairs to infrastructure in the area, working to restore individual customers.

Customers who can take power should have power, except for several isolated cases.

Lakeview

General Street Boundaries:
Robert E. Lee Blvd. to I-610

Area received flooding and requires infrastructure repair.

Expected time to begin serving individual customers who can safely take power and have been issued permits is 4-6 weeks. However, estimated time to totally rebuild electrical distribution infrastructure is 3-6 months.